Markups in Milestone Estimates/Budgets

Milestone Estimates and Budgets can include direct and indirect costs. Depending on how the cost data was entered, indirect costs will be divided into the following markup sections.

Incorporated Item Markups

When using the Copy From workflow with the Running Total, the Item Markups from all Accepted Items will be grouped together in the Incorporated Item Markups section. This table will also include a Source column which tells you the Item each markup originated from.

Caution: This is not a live link with Items so any changes here will not be reflected in the Items these markups were copied from.

Milestone Markups, Contingencies, and Allowances

Milestone Estimates and Budgets each have a Milestone Markups, Contingencies, and Allowances section where you can enter indirect costs.

Incorporated Item Draws

When using the Copy From workflow with the Running Total, the Contingency and Allowance draws from all Accepted Items will be grouped together in the Incorporated Item Draws section. This table will also include a Source column which tells you the Item each markup originated from.

Note: This table is read-only and can't be edited.

Owner Costs

Track Owner Costs separately from Milestone Markups for a complete view of the total project costs. The Owner Costs table is below the Cost of Construction. These costs do not impact the project's Running Total but do appear in reports.


Tip: For detailed instructions on how to manage markups in Join, check out the Working With Markups article.